Is the disconnection of an activity before the completion of activities in a project network diagram?

  • 1004 Accesses

  • 1 Citations

Part of the Springer Optimization and Its Applications book series (SOIA,volume 153)

Abstract

The objectives of this chapter are to:

  • Discuss the importance of PERT and CPM techniques for project management.

  • Distinguish between PERT and CPM network techniques.

  • Discuss the different phases of any project and various activities to be done during these phases.

  • Draw the network diagrams with single and three-time estimates of activities involved in a project.

  • Determine the critical path and floats associated with non-critical activities and events along with the total project completion time.

  • Determine the probability of completing a project within the scheduled time.

  • Establish a time-cost trade-off for completion of a project.

Author information

Authors and Affiliations

  1. Department of Mathematics, The University of Burdwan, Burdwan, West Bengal, India

    Asoke Kumar Bhunia & Ali Akbar Shaikh

  2. Department of Mathematics, Raniganj Girls’ College, Raniganj, West Bengal, India

    Laxminarayan Sahoo

Authors

  1. Asoke Kumar Bhunia

    You can also search for this author in PubMed Google Scholar

  2. Laxminarayan Sahoo

    You can also search for this author in PubMed Google Scholar

  3. Ali Akbar Shaikh

    You can also search for this author in PubMed Google Scholar

Corresponding author

Correspondence to Asoke Kumar Bhunia .

Rights and permissions

Copyright information

© 2019 Springer Nature Singapore Pte Ltd.

About this chapter

Cite this chapter

Bhunia, A., Sahoo, L., Shaikh, A. (2019). Project Management. In: Advanced Optimization and Operations Research. Springer Optimization and Its Applications, vol 153. Springer, Singapore. //doi.org/10.1007/978-981-32-9967-2_14

Download citation

  • .RIS
  • .ENW
  • .BIB
  • DOI: //doi.org/10.1007/978-981-32-9967-2_14

  • Published: 10 January 2020

  • Publisher Name: Springer, Singapore

  • Print ISBN: 978-981-32-9966-5

  • Online ISBN: 978-981-32-9967-2

  • eBook Packages: Mathematics and StatisticsMathematics and Statistics (R0)

R4R Team

R4Rin Top Tutorials are Core Java,Hibernate ,Spring,Sturts.The content on R4R.in website is done by expert team not only with the help of books but along with the strong professional knowledge in all context like coding,designing, marketing,etc!

OMCQ.in

  • Graduate
  • PG
  • Engineering
  • English
  • GK
  • Reasoning
  • Management
  • Quiz Section
    • Current Affairs
    • MBA Quiz

OMCQ.in

  • Graduate
  • PG
  • Engineering
  • English
  • GK
  • Reasoning
  • Management
  • Quiz Section
    • Current Affairs
    • MBA Quiz

Question: ___is the disconnection of an activity before the completion of activities in a Project network diagram.

  • A. dangling
  • B. looping
  • C. dummy
  • D. none of the above
Answer

Answer C. dummy

Give online quiz test

Yes! You can also try Management Science FREE MCQ Quiz and improve your speed and knowledge

Post navigation

Previous Post

Next Post

Related Question

A place for buying and selling activities is called

The exchange value of a good service in terms of money is

Selling the same product at different prices is known as

The words used to convey the advertisement idea is

Advertisement promotes

Agricultural products are

The social aspect of marketing is to ensure

The orange juice manufacturers know that orange juice is most often consumed in the mornings. However, they would like to change this and make the drink acceptable during other time periods during the day. Which form of segmentation would they need to work with and establish strategy reflective of their desires

The typical method of retail operation used by supermarkets and catalog showrooms is called

Marketing creates profit by creating ___ to the buyer

Leave a Comment

Your email address will not be published.

Type here..

Name*

E-mail*

Website

Please enter an answer in digits:

four × 1 =

What do you call if the disconnection occurs in an activity in the network diagram?

1. Dangling. To disconnect an activity before the completion of all activities in a network diagram is known. as dangling.

What is dangling and redundancy in networking system?

A loop can be formed if an activity were represented as going back in line. Dangling To disconnect an activity before the completion of all the activities in a network diagram is known as Dangling. Redundancy If a dummy activity is the only activity emanating from an event and.

What is dangling error in the network diagram?

If a certain activity gets disconnected before the completion of all the activities in network, it results in an error called dangling. An error of dangling goes against the rule that there should be only one end event, that is an event from which no activity originates.

What represent the start or completion of an activity and does not consume time?

The purpose of dummy activity is to maintain the logic of a network diagram. Since no real activity takes place between two such events, the dummy activity does not consume any resources. It also does not consume time duration. Dummy activities are used only in case of absolute necessity.