Start To Finish is a logical relationship (or dependency) in which a successor activity cannot finish until its predecessor activity has started. Show
Start to Finish (SF) is one of the four activity relationships of project management. These are used while preparing project schedule. The other three relationships are:
Let us understand SF relationship in greater depth by using examples, Gantt Chart, Network Diagram, and Mathematical formulas.
Start to Finish Relationship (Dependency) in Project ManagementAs per the PMBOK Guide “Start To Finish is a Logical Relationship in which a Successor Activity cannot finish until a Predecessor Activity has started”. However a better definition is, “Start to Finish is a Logical Relationship in which finishing event of a Successor Activity is dependent on the starting event of a Predecessor Activity”. To understand the above definition, let us look at the events of an activity and not the whole activity. The two distinct events of any activity are:
In SF relationship, the Finish event of the Second Activity is dependent on the Start event of First Activity. The Second Activity is called the Successor and the First Activity is called the Predecessor. You can also look at Max Wideman’s Glossary for a complete set of PDM definitions. Note: An activity or task relationship is loosely termed as project dependency. However, these two terms are different. A relationship between two activities can be established only if one activity is dependent on the other. Just like relationships, there are four type of project dependencies. Let us consider two activities X and Y. X and Y are predecessor and successor activities respectively. The following examples show SF relationship between X and Y:
Representation of Start To FinishGantt ChartAn SF relationship can be visually depicted using using Time Scaled Bar Charts, which are popularly known as Gantt Charts. Let us consider two activities A and B.
The Gantt Chart below shows SF relationship between A and B. As per the above diagram B’s Finish is dependent on A’s Start, which means that B can Finish(F) as soon as A Starts(S). In the above example, A and B together are scheduled to be completed in 4 days. Project Network DiagramAn SF relationship can also be drawn by using Precedence Diagramming Method (PDM), which can be visually depicted by Project Network Diagrams. Let us again consider the above two activities A and B. The Network Diagram below shows SF relationship between A and B. Mathematical FormulasAgain considering the above two activities A and B and using 0 method, we can mathematically represent the relationship between A and B as: B(F) = A(S) Or, if we use 1 method, we can say that: B(F) = A(S) – 1 Start to Finish with Lead and LagSF relationships can be further modified by introducing Lead and Lag modifiers. The following Lead and Lag examples use 0 method representation. Two activities J and K having SF relationship with 1 day of Lead: K(F) = J(S) – 1 day Two activities L and M having SF relationship with 2 days of Lag: M(F) = L(S) + 2 days Finish to Start is Different from Start to FinishFS is the most common and natural relationship but it cannot represent every sequence of activities. Although SF can be mathematically transformed to FS to achieve seemingly similar results, the mathematical transformation modifies and tampers the natural logic. Let’s revisit the Guard example from the previous section to understand why SF is more natural than FS. In the above example, there were two Guards who are doing a shift duty – Evening Guard (E) and Morning Guard (M). In a natural scenario, M can “Finish” her/his duty only “only after” E “Starts” his/her duty. The critical point here is that “M cannot Finish her/his duty even one minute before E Starts”, otherwise it will be tantamount to abandoning the post. Since M cannot abandon the post, she/he has to guard the post even if E gets delayed in starting her/his duty. The Finish of M is logically dependent on Start of E. SF is not a very difficult concept to understand but sometimes it is confused with Finish to Start (FS) relationship. Some authors (incorrectly) claim that FS and SF are essentially same but it is not true. Over to YouPDM Relationships can be represented by using mathematical equations. However, not all mathematical relationships represent the natural logic. While making a project schedule, you should ensure that all dependencies follow the natural logic and are true in the real world. Do you think SF relationship is useful in real projects? Have you ever used it in you project(s)? Or have you seen it being used? I would love to hear from you. PMP Exam FormulasI have also compiled a PMP Formulas Cheat Sheet. It contains 45 formulas and 57 abbrviations. It will help you in your exam prep. It is the best and most comprehensive cheat sheet based on the PMBOK Guide 6th edition. You can download it free of cost for your studies. If you are looking beyond a cheat sheet, then I would suggest you to buy detailed PMP Exam Formula Study Guide by Cornelius Fichtner. It contains detailed explanations of all the formulas along with examples and 105 practice questions. Disclosure: This article contains affiliate links - it means that, if you buy from any of these links, then I will receive a small commission that would help me in maintaining this blog for free. However, for you, there is no extra cost. I recommend only those products that I believe will definitely help the certification aspirants. During which relationship is the from activity unable start until the two activity is started?A start-to-start relationship exists if one activity cannot start until another activity starts. A finish-to-finish relationship exists if the one activity cannot finish until another activity finishes. A start-to-finish relationship exists if one activity must start before another can finish.
During which relationship is the from activity unable start until the to activity is started a startStart To Finish is a logical relationship (or dependency) in which a successor activity cannot finish until its predecessor activity has started.
Which of the following describes a relationship where the from activity must be finished before the to activity can be finished?A finish-to-finish dependency is a relationship in which the "from" activity must be finished before the "to" activity can be finished.
What type of sequencing relationship is used when the second activity does not start until the first one is completed?In a finish-to-start relationship, the successor activity cannot begin until the predecessor activity has completed. This is the most frequently used logical relationship and is the default setting for most project-scheduling software packages.
|