Which of the following refers to the amount of individual resources that a schedule requires during a specific time period?

____ refers to the amount of individual resources an existing schedule requires during specific time periods.

____ refers to the amount of individual resources an existing schedule requires during specific time periods.

a.Resource loading
b.Resource leveling
c.Resource allocation
d.Resource requesting

Answer: A

Learn More :

4)The amounts of individual resources that a schedule requires during specific time periods are referredto as the resource's.A)loadinB)capacityC)constraintD) draggIntroduction to Project Management

5)A resource loading form can be generated once you have developed

Get answer to your question and much more

6)The process that addresses the complex challenges of project constraints is known as.

Get answer to your question and much more

7)Because resource management is typically a multivariate, combinatorial problem (i.e., on that ischaracterized by multiple solutions involving literally dozens, hundreds, or even thousands of activityvariables)truly correct answers are not possible.e

Get answer to your question and much more

Which of the following is a column chart that shows the number of resources assigned to a project over time?

The staffing management plan often includes a resource histogram, which is a column chart that shows the number of resources assigned to a project over time.

What needs is at the highest level in Maslow's structure?

Self-actualization is at the top of Maslow's hierarchy of needs. This need refers to the desire to reach our full potential. According to Maslow, this need can only be met once all of the other needs are satisfied.

Which term refers to the amount of individual resources an existing schedule requires during specific time periods?

Time-phased resources. describes amount of individual resources an existing schedule requires during specific time periods.

What information is usually provided on a resource usage calendar?

12) What information is usually provided on a resource-usage calendar? A) The tasks, the precedence requirements, and the money per unit time needed to reduce them. B) The personnel, their hourly wage or salary, and the number of hours per week they are available.