Which type of float shows the time an activity can be delayed extended without affecting any succeeding activities?

Leads, lags and float are concepts used in schedule development process. The process of schedule development includes: identification of all activities, sequencing all activities based on dependency, estimating duration of each activity and finalizing the schedule. Leads, lags and float are used as part of activity sequencing process. All activities once sequenced will form a schedule network diagram. Let us first look at the definition of all these three attributes.

Float

Float (also known as slack) is the amount of time by which the start of an activity can be delayed without delaying the project completion time. Every task will have following set of start and finish time. 

  • Earliest start time (ES) - The earliest time, an activity can start once the previous dependent activities are over.
  • Earliest finish time (EF) - This would be ES + activity duration.
  • Latest finish time (LF) - The latest time an activity can finish without delaying the project.
  • Latest start time (LS) - This would be LF - activity duration.

Float time of an activity can be calculated by taking the difference between Late Start (LS) and Early Start (ES) OR between Late Finish (LF) and Early Finish (EF).

Float = LS-ES  OR 

=LF-EF

A positive float time indicates the flexibility we will have in delaying the specific activity without delaying the project completion time.

Typically, while doing scheduling, the critical path tasks will have zero float and the non-critical path tasks will have a positive float. That means non-critical path tasks can be delayed to certain extent without compromising on the project completion time. Float time information of tasks is very useful to the project team for taking scheduling decisions when there will be resource constraints.

Lag:

Lag is the amount of wait time between two tasks. Or in other words, lag is the amount of time by which a successor activity will be delayed. Lag can be used in all the four logical relationships in scheduling, such as Finish-to-start (FS), start-to-start (SS), finish-to-finish (FS) and start-to-finish (SF).

In below example, Task A and B have a Finish to Start (FS) relationship. Ideally both A and B should get finished on the 12th day. But when we insert a waiting of time of 2 days before B can start, then both A and B will get completed only on the 14th day.

Which type of float shows the time an activity can be delayed extended without affecting any succeeding activities?

Lead:

Lead is the amount of time a successor task can be accelerated. Lead can applied only on finish-to-start relationship between two activities. We can see the below example. In the below example, task B can start 2 days before the completion of task A. Hence the start of task B, which ideally would have been on 6th day, will not start on 4th day.

Conclusion:

Float, lead and lag are very important concepts and information for the scheduling team. A PMP training course ensures you get a hold of these concepts. These are used to optimally identify the dependencies and the associated constraints. Float information is useful in resource allocation when there are resource constraints. Lead is used for accelerating start of tasks (fast tracking) for reducing project timelines. Lag is used for ensuring that required idle or wait time after a task is appropriately provisioned.

The maximum amount of time that an activity can be delayed without extending the completion time of the overall project is called:

  1. Duration

  2. Time Limit

  3. Float

  4. Critical path

Answer (Detailed Solution Below)

Free

10 Questions 10 Marks 10 Mins

Explanation

1. Float

  • It is associated with activity times.
  • It is analogous to the slack of events in PERT.
  • It is the range with which start or finish activity may fluctuate without affecting the project completion time.
  • Floats are of the following types:
    • Total float: The time span by which starting or finishing of an activity can be delayed without delaying the completion of the project. It is the maximum available time over the activity completion time.
    • Free float: The delay which can be made without delaying succeeding activities. It affects only preceding activities.
    • Independent float: It is the minimum excess available time that exists without affecting any of the succeeding or preceding activities.
    • Interfering float: It is similar to head event slack.

So, 

A float (or slack) in a critical path method (CPM) is the amount of time that a task can be delayed without causing any delay to Subsequent tasks and project completion date.

2. The critical path will be the longest path in the network requiring the maximum amount of time, but it will represent the minimum duration that is required to complete all the activities i.e. completion of a project.

Which float the amount of time by which an activity can be delayed without impacting the project completion time?

Total Float (TF) It is the amount of time by which an activity can be delayed without delaying the project duration.

What are the three types of float?

Types of float.
Total float. ... .
Free float. ... .
Project float. ... .
Interfering float (INTF) ... .
Independent float (INDF) ... .
Determine the critical path. ... .
Establish the earliest finish (EF) date. ... .
Identify the latest finish (LF) date..

What is total float and free float?

Simply put, Total float is the amount of time that an activity can be delayed without delaying the project. On the other hand, free float is the amount of time that an activity can be delayed without delaying the early start of its successor.

Which float is the amount of time that the activity completion time can be delayed without affecting the earliest start time of the immediate successor activity in the network?

Free float: It is the amount of time that the activity completion time can be delayed without affecting the earliest start time of the immediate successor activities in the network.