What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

Right on! Give the BNAT exam to get a 100% scholarship for BYJUS courses

No worries! We‘ve got your back. Try BYJU‘S free classes today!

No worries! We‘ve got your back. Try BYJU‘S free classes today!

No worries! We‘ve got your back. Try BYJU‘S free classes today!

Solution

The correct option is A Free floatFree float (FF) : ∙ It is defined as the amount of time by which an activity can be delayed without affecting the early start time of the succeeding activity. ∙ In other words it is that portion of total float that can be used by an activity without delaying any succeeding activity. Free float =Total float-Heat event slack Note : 1. total Float (FT): The difference between the maximum time available and the actual time required for the completion of the activity. FT =(Maximum available time)-Actual time required Total Float = LST-EST EST → Early start time LST → Latest start time = LFT -tij EFT → Early finish time = EST +tij LFT → Latest finish time 2. Independent float FID: It is defined as the amount of time by which an activity can be delayed without affecting the succeeding activity and preceding activity. Independent float = Free float-Tail event slack 3. Interfering Float (FIT) : ∙ It is defined as the difference between the total float and free float of an activity. ∙ It is also equal to the slack of head event of head activity

What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

by Usman Islam , Senior Operation Coodinator , SGB International FZE
6 years ago

free float is the correct answer...........

What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

by TARIG BABIKER AL AMIN , Planning & Researcher , Assistance inspector , الشركة السودانية للمناطق والأسواق الحرة المحدودة
6 years ago

B : is the right answer - Total float : is the amount of time that an activity can be delayed without delaying the project completion date , because C : Free float : is the amount of time that an activity can be delayed without delaying the Early Start of its successor activity

Free Float Option " C "              .

What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

by Rami Assaf , Plant Manager , Al Manaseer group
6 years ago

The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as?

3. free float

What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

by Mohammed Ashraf , Director of International Business , Saqr Al-Khayala Group
6 years ago

It shows option "C" is suitable one. 

Free float...is the answer

What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

..................   c .      free float

What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

by Yaqoub Alomar , Civil Engineer , Al-Zubeir municipality
6 years ago

C.     free float

*****************

What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

by Mohamed Helal , Project Manager , GROUP CONSULT INTERNATIONAL
6 years ago

The correct answer is option (C.free float)

What is the duration by which the completion time of any activity can be delayed without affecting the start of any of succeeding activities?

I think the correct answer is C.free float

thanks for invition ,,,,,,,,,,

my choice is option C 

Popular Searches

What is the amount of time that a task can be delayed without affecting the subsequent task?

In project management, float or slack is the amount of time that a task in a project network can be delayed without causing a delay to: subsequent tasks ("free float") project completion date ("total float").

Which is the duration by which an activity can be delayed without deleting the completion of the project?

Float, sometimes called slack, is the amount of time an activity, network path, or project can be delayed from the early start without changing the completion date of the project.

What is the amount of time that a task can be delayed?

A float (or slack) in a critical path method (CPM) is the amount of time that a task can be delayed without causing any delay to Subsequent tasks and project completion date. 2.