Which of the following risk strategies involves taking steps to minimize the impact and likelihood of occurrence?

A risk can be a Threat, i.e., a risk with a negative impact on project objectives, or it may be an Opportunity, i.e., a risk which brings a positive effect on project objectives, and accordingly, there are different strategies to deal with negative and positive risks, when it comes to Project Management.

Positive Risk Management Strategies

  1. Exploit

    Exploitation increases the chances of making a positive risk happen, leading to an opportunity. As a project manager, you assigned sufficient and efficient resources to take advantage of this opportunity. This approach reduces the uncertainty associated with a positive risk by ensuring that it happens.
  2. Share

    When the project team themselves are not fully capable of taking advantage of the opportunity they might call in another company to partner with. The expertise of another company is leverage to maximize the return out of the opportunity. Examples of sharing opportunity include forming risk-sharing partnerships, teams, unique purpose companies, or joint ventures. In this all parties gains as per their investment and action.
  3. Enhance

    Enhancing involves increasing the probability of occurrence of the risk and expanding its impact. This is done by identifying and influencing the various risk triggers. An example of enhancing an opportunity includes adding more resources to project activities to finish it earlier.
  4. Accept

    This involves taking advantage of the positive risk as it happens but not actively pursuing it.  It is just like an opportunity coming and being accepted without much pre-planning.

Read more: Risk Management Cycle: Process and Framework

Negative Risk Management Strategies

  1. Avoid

     Avoidance eliminates the risk by removing the cause. It may lead to not doing the activity or doing the activity in a different way. The project manager may also change or isolate the objective that is in trouble. Some risks can be avoided by an early collection of information, by improving communication between stakeholders or by use of expertise.
    Example of this approach includes extending the schedule or changing the scope of the project activity. Another example could be a risk which is too hazardous that it may lead to loss of life and is avoided by shutting down the project altogether.
  2. Transfer

    In Risk Transfer approach, the risk is shifted to a third party. The third-party, like insurance company or vendor, is paid to accept or handle the risk on your behalf and hence the ownership, as well as impact of the risk, is borne by that third party. This payment is called a risk premium. Contracts are signed to transfer the liability of risks to the third party.
    Risk Transfer does not eliminate the risk, but it reduces the direct impact of the risk on the project. Few Transference tools are an insurance policy, performance bonds, warranties, guarantees, etc. This approach is most effective in covering financial risk exposure.
  3. Mitigate

    Mitigation reduces the probability of occurrence of a risk or minimizes the impact of the risk within acceptable limits. This approach is based on the fundamental principle that earlier the action taken to reduce the probability or impact of a risk is more effective than doing fixes to repair the damages after the risk occurs.
    Example of mitigating a risk includes the use of advanced technology or best practices to produce more defect-free products. Mitigation may require a prototype development to measure the risk level. In the case where it is not possible to reduce the probability of the risk, the risk impact reduction is targeted by identifying the linkages that determine the risk severity.

    Read more: Project and Program Risk Management

  1. Accept

    Acceptance means accepting the risk, especially when no other suitable strategy is available to eliminate the risk. Acceptance can be passive acceptance or active acceptance.
    Passive acceptance requires no other action except to document the risk and leaving the team to deal with the risks as they occur. In an active acceptance approach, a contingency reserve is designed to recover the losses of time, money, or resources.

Do you have the right skills for the role of a project manager? Take up this PMP® Practice Test and assess yourself!

Contingent Risk Response Strategies

These strategies are implied only when certain events occur. The execution of these strategies happens only under certain predefined conditions. The team waits for sufficient warning signals before implementing these strategies. These signals could be missing the milestones work items or deadlines etc.

These strategies include using Financial reserves, Staffing reallocations, and implementing Workarounds to minimize the loss, repair the damage to the extent possible and prevent a recurrence.

References:

  • Achieve PMP Exam Success, Margaret Chu, Diane Altwies, Edward Walker, JRoss Publishing.
  • 3rd Edition Head First PMP, Jennifer Greene and Andrew Stellman, O’Reilly, 2nd Edition
Learn to deliver digital-age transformational projects and excel in the field of project management with Simplilearn’s project management training.

What are the 4 risk response strategies?

Since project managers and risk practitioners are used to the four common risk response strategies (for threats) of avoid, transfer, mitigate and accept, it seems sensible to build on these as a foundation for developing strategies appropriate for responding to identified opportunities.

What are some strategies to minimize risk?

Let's talk about four different strategies to mitigate risk: avoid, accept, reduce/control, or transfer..
Avoidance. If a risk presents an unwanted negative consequence, you may be able to completely avoid those consequences. ... .
Acceptance. ... .
Reduction or control. ... .
Transference. ... .
Summary of Risk Mitigation Strategies..

Which action involves reducing the impact of a risk event by reducing the probability of its occurrence?

Mitigate. Mitigation reduces the probability of occurrence of a risk or minimizes the impact of the risk within acceptable limits.

Which of the following strategies means that impact of the risk will be reduced?

Risk management is now recognized as one of the most important project management tasks. ... .